Executive Summary

The South Australian Court of Appeal (Court of Appeal) in Goyder Wind Farm 1 Pty Ltd v GE Renewable Energy Australia Pty Ltd & Ors has delivered a landmark judgment.

The decision provides much needed clarity as to when, and in what circumstances, a contractor may (and may not) repeat claims made under the statutory security of payment (SoP) regime.

While this is a decision of the Court of Appeal and its direct impact will be limited to projects in South Australia (SA), the decision is likely to be applicable under the equivalent SoP regimes which exist in all other Australian states and territories (except the Northern Territory). The other interstate SoP regimes are drafted in similar, and often exactly the same, terms, albeit the various regimes also differ in other respects.

The Court of Appeal considered the following issues:

The Court of Appeal held:

Background

The case relates to a significant wind farm project in country SA. The joint venture Contractor claimed it was entitled to various extensions of time and delay costs attributable to Principal caused access delays. These access delays were alleged to have been caused by delays in obtaining environmental approvals.

The Contractor issued two separate payment claims (in February 2024 and April 2024) in respect of different reference dates. It subsequently made two separate applications for adjudication of those payment claims, both of which resulted in adjudication determinations. The Principal sought to quash the second adjudication determination by way of judicial review, on the basis that the second adjudication application was a reagitation of the first. Both the primary judge and the Court of Appeal found that there was no overlap between the first and second payment claims.

The judge at first instance dismissed the Principal’s application for judicial review. Whilst the judge accepted that the two claims arose from a common cause of delay, it did not follow that delay costs arising from the same delay constituted a singular claim for delay. The Principal appealed the judge’s decision.

Court’s Findings and Commentaries

The Court of Appeal dismissed the appeal. The Court of Appeal, having regard to the provisions of s32 of the SoP Act, did not consider the common law concept of issue estoppel to be applicable. It then followed that an extended doctrine of Anshun estoppel was similarly inapplicable. The Court of Appeal held that this was not to say that there is no scope for the operation of a doctrine of preclusion under the SoP Act; however, this would likely be made pursuant to an application for an abuse of process.

The Court of Appeal went on to consider whether the Contractor’s submission of two payment claims for delay costs amounted to an abuse of process, however, it could not conceive of a situation where nonoverlapping claims for delay costs amounted to an abuse. That is, there would at least need to be factual repetition of claims for there to be an abuse of process, noting, however, that repetition alone may not be sufficient.

Takeaways

For the construction industry, the key takeaways are:

Leave a Reply

Your email address will not be published. Required fields are marked *